Project Summary
- Calgary, AB
- Completed 2015
What Mattered to the Client
Schedule certainty, constructability, and delivering a river crossing that met strict geometric and environmental constraints.
The Calgary Exhibition and Stampede required a new vehicular bridge to provide reliable access to Stampede Park. The project needed to be designed and constructed within a compressed timeline, with completion aligned to the annual Calgary Stampede.
Site conditions introduced significant challenges. The bridge had to clear flood levels while maintaining a low enough profile to pass beneath adjacent infrastructure. At the same time, minimizing in-stream work was critical to avoid environmental restrictions and permitting delays.
Balancing these constraints required a solution that could achieve a clear span across the river, reduce construction risk, and deliver long-term performance within budget.
What we Built Together
A single-span cable-stayed bridge designed to meet tight geometric requirements while eliminating the need for river piers.
The bridge spans approximately 48.5 metres across the Elbow River, carrying two lanes of traffic and a pedestrian walkway. The structure features a post-tensioned concrete deck supported by cable stays anchored to twin pylons, allowing for a slender deck profile within strict height limitations.
By removing the need for in-river supports, the design reduced environmental impact and simplified construction sequencing. The bridge was constructed using an innovative approach that allowed the deck to be cast in a single stage, supported by temporary girders spanning the river.
As the first vehicular cable-stayed bridge in Alberta, the project introduced a structural solution that combined efficiency, durability, and a strong visual identity.
Our Role
Lawson Projects acted as Project Manager, supporting the client and project team through planning, coordination, and construction delivery.
Our role focused on maintaining alignment between design development and an aggressive construction schedule. With design and construction progressing concurrently, proactive coordination and decision-making were essential to keep the project moving forward.
We worked closely with consultants and contractors to manage risk, support staging and sequencing decisions, and ensure that project objectives were met within the required timeframe.
The Result
A highly efficient and visually distinctive river crossing delivered within a constrained schedule and complex set of requirements.
The Elbow River Cable-Stayed Bridge provides critical access to Stampede Park while demonstrating the effectiveness of alternative structural solutions for medium-span crossings. Delivered on time for Stampede operations, the project stands as a successful integration of engineering, constructability, and site-specific design.